Contact
Hit enter to search
Location
Reay, Thurso, North Scotland
Main Contractor
Keltbray Energy
Value
Undisclosed
Project Length
Introduction

Keltbray Energy have been engaged by SSEN to deliver the 33/132kV substation, 132kV overhead line and underground cable connection to the existing Dounreay 132kV Substation located just outside Thurso. The deliverables include the design, build, installation and commissioning of all aspects of the aforementioned elements of construction.

  • Keltbray Energy’s fist self-deliver renewables project
  • Full substation build with internal AIS Equipment Build, test and commissioning
  • 5.5 hectares of Forestry Tree Felling
  • 4km 60 pole OHL route
  • 1km Trefoil Under Ground Cable route terminating in the Dounreay Power Station GIS Hall