Keltbray supported Mace in the redevelopment of 100 New Bridge Street, delivering a programme of structural alterations and new steel and concrete works across the existing building. The scope included a full soft strip, cladding removal, demolition of plant rooms and satellite cores, and selective slab and column removal. The team also designed, supplied and installed new steelwork, including a three‑storey office extension and a Vierendeel truss to replace the former reinforced‑concrete core. 

Sustainability targets shaped the project from the outset. The scheme aimed for high circular‑economy performance, achieving extensive material retention and waste reduction. By reusing 91% of the reinforced‑concrete lift cores and 85% of the reinforced‑concrete walls, the team significantly reduced the need for new materials. Mace estimated that these measures saved 1,795 tonnes of CO₂e, supported by early collaboration between Helical, Keltbray, Mace and the wider project team. 

The project demonstrated how the circular economy can be integrated into central London redevelopment. By combining structural demolition, steelwork installation and new sub and superstructure elements with a sustainability‑led approach, the team delivered a scheme that met both contemporary performance standards and carbon‑reduction ambitions. 


Project outcomes  

  • Structural delivery

    Successful structural delivery, achieved through the completion of complex demolition, strengthening and new steelwork while maintaining programme certainty. 

  • Sustainability gains

    Major sustainability gains, driven by significant CO₂e savings and high levels of material retention through circular‑economy measures. 

What we stand for

Target reuse
95%
The project targeted a reuse and recycling of construction waste
Retained
91%
Reinforced concrete lift cores retained
Walls retained
85%
Reinforced concrete walls retained
Avoided CO2e
1,795 tonnes
CO2e were avoided through circular economy measures

What the client says

“100 New Bridge Street embodies Helical’s ‘carbon-friendly new build’ model, retaining as much of the existing building as possible while creating a building that meets the demands of today’s occupiers. Early engagement and collaboration with Keltbray has been key in delivering the ambitions of this project.”

Laura Beaumont

Head of Sustainability, Helical