Keltbray Lifting Services, working alongside Keltbray Decommissioning, supported Costain with the planned removal of the Allerdeen Bridge superstructure. The works involved the controlled lifting and removal of 12 steel span beams, with individual lifts of up to 30 tonnes, requiring a carefully sequenced and risk‑managed approach.  

Keltbray provided end‑to‑end lifting support, including lift plans, crane studies and method statements, utilising two 450‑tonne mobile cranes operating from both abutments. Through disciplined planning and close coordination with the project team, the bridge 


Key Facts 

  • Two 450‑tonne mobile cranes 
  • Removal of 12 steel span beams 
  • Lifts of up to 30 tonnes 

Project scope:

  • Full lifting planning and execution for bridge dismantling works

  • Lift plans for removal of 12 steel beams

    (Up to ~30 tonnes) 

  • Coordination of dual crane operations

    (2 × 450 tonnes mobile cranes)

  • Sequencing to maintain structural stability during removal

  • Technical supervision and compliance with LOLER, PUWER, BS 7121